This Article is From Sep 18, 2019

Bhubaneswar Airport To Be Partially Shut For 8 Months Due To Repair Work

The flight services would be rescheduled as the re-carpeting work of the runway will be taken up from November. The re-carpeting of the runway would take place in two phases.

Advertisement
Bhubaneshwar News

Biju Patnaik Airport in Bhubaneswar to remain partially closed due to runway re-carpeting

Bhubaneswar:

The Biju Patnaik International Airport in Bhubaneswar will remain partially closed for eight months due to the runway re-carpeting work from November 1 to March 31, said an official on Tuesday.

The flight services would be rescheduled as the re-carpeting work of the runway will be taken up from November. The re-carpeting of the runway would take place in two phases.

"We are planning for runway re-carpeting with effect from 1st November to 31st March, 2020 from 10 pm to 5.30 am. We have requested Director General of Civil Aviation (DGCA) for permission. Once we get the approval, the work will start," informed airport director Suresh Chandra Hota.

He said there will be a closure of flight operations during this period in the night and airlines have to reschedule.

Mr Hota said that flight operation during daytime at the airport will be suspended from April 1 to June 30, 2020 from 10.30 am to 6 pm.

Advertisement

The re-carpeting of the runway was last taken up at the airport in 2007.

The airlines have been intimated about the re-carpeting of the runway by Airport Authority of India (AAI), said Mr Hota.

Advertisement
Advertisement