Trial runs on the main line for the operationalisation of the 17-km Duhai-Sahibabad priority section of the ambitious Delhi-Meerut RRTS corridor will begin early December, a senior official said on Friday.
The priority section is expected to get operationalised by March next year, Managing Director of the National Capital Region Transport Corporation (NCRTC), Vinay Kumar Singh, said.
Trial runs have been started in the depot already and the trains are "behaving perfectly" as was planned and designed, he said.
The NCRTC is implementing India's first Regional Rapid Transit System (RRTS) between Delhi and Meerut.
During a media interaction held at the site of the under-construction station of Anand Vihar on the 82-km Delhi-Ghaziabad-Meerut RRTS, he said after the Duhai-Sahibabad priority section, "the next section that we will open, will be the Duhai-Meerut South section and plan is to operationalise it by December next year".
The entire Delhi-Ghaziabad-Meerut RRTS is targeted to be operational by 2025. Its Duhai-Sahibabad priority section in Uttar Pradesh's Ghaziabad is expected to be operational by early 2023, the NCRTC had earlier said.
Asked when will the trial runs begin for the priority section and by when it is expected to be operationalised, Singh said, "Trial runs have already started. Presently, we are doing trials in the depot. Two trains we already have, and the next train will be coming next week in the depot".
"Various kinds of trials are undertaken and involves traction system, rolling stock and signalling system, which are new here. First we integrate the coaches, then we test brake system.
"These trains have automatic train protection (ATP), and that testing we have done, and these trains are behaving perfectly as was planned and designed," he said.
The top official of the NCRTC said, on the main line, trials will begin in the first week of December, adding, by February-March next year, the priority section is expected to be operationalised.
The priority section has four stations -- Sahibabad, Ghaziabad, Guldhar and Duhai.
On a query on high-speed trials, he said, "We have to do it in a combined manner, with multiple agencies and we have sought dates from multiple agencies for it".
Asked about the fare structure, Singh said, "A decision on it will be taken soon, work is in very advanced stage".
On the subsequent section of the NCRTC that it plans to operationalise after the priority section, he told reporters that Duhai-Meerut South section is quite long and includes Murad Nagar, Modi Nagar South, and Modi Nagar North.
"Meerut South will take people to outer area of Meerut and our plan is to operationalise it by December next year," he said.
Some other states like Haryana, Uttar Pradesh, and Telangana too desire to have similar RRTS corridors, the official said, adding that Uttar Pradesh wants it between Delhi and Kanpur.
Sarai Kale Khan is one of the major stations on the 82-km-long Delhi-Meerut RRTS corridor. The RRTS corridor would cut down the travel time between Delhi and Meerut to around 55 minutes from the current three-four hours by road.
Each train that will run on the RRTS corridor will primarily consist of six coaches, comprising five standard coaches and one premium class coach. One coach in each train will be reserved for women, another senior official of NCRTC said.
A standard-class coach will have three doors on one side and the premium-class coach will have two doors. Based on this, a total of 17 platform screen doors (PSDs) will be installed on each platform of RRTS stations.
(Except for the headline, this story has not been edited by NDTV staff and is published from a syndicated feed.)
Featured Video Of The Day
"Ad Money Will Be...": Supreme Court Warns AAP Over Funds For Rapid Rail Project NaMo Bharat Ridership Likely To Cross 10,000 Mark On First Day Delhi-Meerut Rapid Rail 'Priority Section' To Start In Weeks. Details Here Maharashtra, Jharkhand Counting Today, Key Bypoll Results In 15 States "Thousand Times Better...": Delhi Lt Governor's Surprise For AAP's Atishi "Violation Of Sovereignty, Abuse Of Power": Kanwal Sibal On US Report On Adani Group Budget, Debt: Donald Trump's Treasury Chief Faces Urgent Challenges Who Is Nikita Hand? Woman Wins Sexual Assault Case Against MMA Fighter "Those Who Can't Pay...": Anupam Mittal On Deepinder Goyal's Job Offer Track Latest News Live on NDTV.com and get news updates from India and around the world.