The Airports Authority of India (AAI) accomplished an incredible milestone by completing re-carpeting work at Calicut International Airport in a record time of 120 days, much ahead of the scheduled date, an official statement said on Tuesday.
The project aimed at enhancing the safety standards of the airport was completed with an estimated project cost of Rs 60 crore including re-carpeting of the 2.86 km runway, and fixing of Runway Centre Line lights and Touchdown Zone lights.
The re-carpeting work of any runway of over 2.5 km takes 8 to 9 months on average. The work for re-carpeting the runway of Calicut International Airport commenced on January 27, 2023, and successfully completed on June 2, 2023, well before the onset of monsoons in Kerala.
The re-carpeting work included milling - i.e. removal of previous bituminous layer surface, re-carpeting (2860 meters long runway, runway shoulders, taxiway, and RESA), providing glass fiber reinforcement grid and laying of Runway Centre Line Lighting (RCLL) and Touch Down Zone Lights (TDZ), which was completed in just 120 days.
This feat could be achieved by AAI owing to its meticulous planning and efficient project monitoring and execution.
According to the statement, airport runways are built to comply with internationally mandated standards. Frequent landing and take-off of flights lead to wear and tear of runways over a period of time. Natural weather phenomena like rain and sun also affect the runway surface.
Thus, depending on the volume of traffic and the variety of aircraft, the runway needs to be re-carpeted as per the operational requirements. This is done by taking into consideration various factors including, how busy the airport is and the variety of aircraft that it handles etc.
The re-carpeting of the 2.86 km Calicut Airport Runway and allied works were planned meticulously. As the runway was closed for operations during the day (NOTAM initiated for closure of runway), all daytime flights were rescheduled for the night. Since the closure of the runway was from 10 AM to 6 PM, this didn't have any major impact on the night traffic.
The work was planned in such a way that the runway was readied for landings and take-offs by 6 PM every day. Although Calicut Airport has 70 to 80 flight movements every day, less than 10 flights operate during day time (between 10 AM and 6 PM) and arrangements were in place to cater to rescheduled flights and the resultant footfall.
Calicut International Airport situated on hilly terrain surrounded by a lush green valley is known for its unique Table-Top runway. The airport is currently handling 70 movements and approximately 4000 passenger footfalls per day, the statement added.
Featured Video Of The Day
Airports Authority Of India Invites Applications For 197 Apprentice Posts, Check Details Airport Authority Of India Recruitment 2024: Applications Open For 90 Apprentice Posts, Check Details Runway Introduces Advanced Camera Control Feature on Gen-3 Alpha Turbo AI Video Generator Pics: Rahul Gandhi's Family Lunch At Iconic Delhi Restaurant Donald Trump Appoints Indian-American, Elon Musk Aide As AI Advisor 'Sunny Leone' Got Rs 1000/Month Under Chhattisgarh Scheme For Married Women 3 Khalistani Terrorists, Who Attacked Punjab Cops, Killed In UP Encounter IBSAT 2024 Registration Deadline Today, Check Details 'Sunny Leone' Got Rs 1000/Month Under Chhattisgarh Scheme For Married Women Track Latest News Live on NDTV.com and get news updates from India and around the world.