This Article is From Aug 29, 2022

Noida Twin Towers Are Now 80,000 Tonnes Of Debris, 90 Days For Clean-Up

Around 35,000 cubic metres or approximately 80,000 tonnes of debris was left after the demolition of the Supertech twin towers. Around 50,000 tonnes of it has been absorbed in the basements, while the remaining would be disposed of in 90 days.

Noida Twin Towers Are Now 80,000 Tonnes Of Debris, 90 Days For Clean-Up
Noida:

With the successful demolition of the Supertech twin towers, India has joined the club of countries that have razed buildings taller than 100 metres, Joe Brinkman of South African firm Jet Demolitions has said.

The illegal twin towers in Noida's Sector 93A were grounded by waterfall implosion technique in a matter of 12 seconds, Brinkman told reporters on Sunday.

The Apex (32 storeys) and Ceyane (29 storeys) towers of Supertech had a height of 103 metres each, according to officials.

Mumbai-based Edifice Engineering, which was tasked with the demolition, had selected Jet Demolitions as its expert partner for the job.

The two had together previously demolished four residential complexes in Maradu municipal area of Kochi, Kerala, in a similar fashion.

"India and Edifice have now joined the 100-metre club of countries which have buildings over this height that have been demolished and that too with residential buildings standing so close to them, making the project extremely challenging," Brinkman, 62, said, heaping praises on the Edifice-Jet team.

"All credit goes to the entire team," he said.

Jet Demolitions holds a distinguished position globally for demolition works.

In November 2019, the firm had grounded the 108-metre-tall Bank of Lisbon building in Johannesburg within a few seconds in an eye-popping event and ensured that a structure barely seven metres next to it was safe too.

Brinkman said the whole process for demolishing the Noida twin towers took 12 seconds.

He said the team's first priority was to ensure that there were no injuries to people during the implosion and no structural damage caused to any of the buildings around.

He added that very few buildings taller than 100 metres have been demolished in a controlled manner across the world.

Edifice Engineering partner Utkarsh Mehta described Brinkman as the "mastermind" of the successful demolition.

He said around 35,000 cubic metres or approximately 80,000 tonnes of debris was left after the demolition. Around 50,000 tonnes of it has been absorbed in the basements of the now-demolished towers while the remaining would be disposed of in 90 days, he said.

"We will have to coordinate with the Emerald Court and ATS Village societies for the disposal since the debris would have to be first processed at the site only and then it would be taken to construction and demolition waste processing centres.

"Coordination would be needed for fixing the timing for work at the site to cause least disturbance to residents," said Mehta.

Jigar Chheda, another Edifice partner, said they took six months to plan the clean execution of the demolition and the whole exercise was a "very challenging" process.

"Days and nights went into the preparation for this day. Over 9,000 holes were drilled for explosives in the two buildings; they had to be most accurate and all this was challenging," Chheda told PTI.

"Getting permission from all authorities concerned, coordinating with multiple agencies, and convincing residents of safety were key effort areas," he said.

Mayur Mehta, project manager for Edifice, said 9,642 holes were drilled and 3,700 kg of explosives were used for the demolition.

"The types of explosives used were Solar coal - with 6 gm, 10 gm, 20 gm, and 80 gm mass. Electric detonators, shock tubes and emulsions were also used. The tubes were placed in a way that some had a 0.5-millisecond explosion capacity, while others had a 7,000-millisecond capacity," he added.

Edifice officials said nine metres of the boundary wall of ATS Village comprising some 900 bricks was damaged.

Several window panes in Emerald Court, as well as ATS Village, were cracked and they had started the process to replace them with new ones shortly after inspection at the site Sunday evening.

.