This Article is From Nov 28, 2023

"Won't Say It Again And Again": Supreme Court Rap For Delhi Over Funds

The Delhi government, which reportedly released Rs 415 crore last week, told the Supreme Court it had now paid all its dues.

Advertisement
India News Edited by

The RRTS project - an 82-km stretch costing nearly Rs 32,000 crore (File).

New Delhi:

The Supreme Court came down hard on the Delhi government Tuesday over delays in paying its share of funds - around Rs 500 crore - for the Regional Rapid Transit System, or RRTS, which is a semi-high speed rail corridor linking to Meerut in Uttar Pradesh, Alwar in Rajasthan and Haryana's Panipat.

"Problem is you have to be arm-twisted to pay money you are obligated to. We will not say it again and again. Pay what you have to..." a top court bench of Justices SK Kaul and S Dhulia said.

The Delhi government, which reportedly released Rs 415 crore last week, told the court it had now paid all its dues. However, demanding "absolute compliance", the court then listed the matter for Saturday.

The strong comments come after the Delhi government was given a week to stump up its share.

An irked court had then told the Delhi government "you have not complied with our order... can't take us for granted", and that it would transfer funds from the ruling Aam Aadmi Party's spending on ads - highlighting its achievements to voters - if the directed sum of Rs 415 crore is not made available.

Advertisement

READ | "Ad Money Will Be...": Supreme Court Warns AAP Over Funds For Rapid Rail Project

As today's hearing began, Justice Kaul said, "At your request, we kept in abeyance for a week (order) to comply with assurance given to this court. Now, please give document which shows compliance."

Advertisement

To this the counsel for the Delhi government said "some transfers" had been made, but this was countered by the senior advocate appearing for the National Capital Region Transport Corporation.

"There has (only) been partial compliance... four months have passed, nothing has come."

Advertisement

The court waved aside questions of payment for other projects and said, "What you (the Delhi government) have to pay elsewhere... if required, we will deal with it. But here the limited point is whether our order has been complied with," Justice Kaul underlined.

Earlier, the Delhi government had expressed its inability to contribute the required funds, after which the court sought a record of funds spent by the ruling AAP on ads over the past three years.

Advertisement

On July 24, top court noted the Delhi government, which had been told to contribute Rs 500 crore for this project, had spent more than Rs 1,000 crore on ads in the last three financial years.

The Delhi government had been told to provide Rs 415 crore within two months.

Advertisement

Last week the Delhi government counsel assured the court full payments will be made.

The RRTS project - an 82-km stretch costing nearly Rs 32,000 crore - entails semi-high speed rail corridors connecting Delhi to Alwar, Panipat, and Meerut. Around 13 km is within the national capital.

The project is managed by the National Capital Region Transport Corporation - a centre-states venture.

With input from agencies

NDTV is now available on WhatsApp channels. Click on the link to get all the latest updates from NDTV on your chat.