This Article is From Jul 16, 2012

Jaipur Metro likely by June 2013

Jaipur Metro likely by June 2013

Representative Pic

Jaipur: The residents of 'Pink City' and visiting tourists are all set for a Metro train ride from June 2013, as authorities have stepped up work for the ambitious dream project, which will cost over Rs 10,000 crore.

"It is very likely that the residents of Jaipur would get their dream of Metro train realised by June 2013," said an official of the state urban development department.

The work of Jaipur Metro is to be completed in two phases. Of this, 55 per cent work on the first phase has been completed and the engineers are working hard to complete the remaining work of this phase.

Under the first phase, which is called IA, the Metro train would run between Mansarovar and Chandpole covering a distance of 9.718 km. Similarly, under the second leg of the first phase, called-IB, the Metro train would run from Chandpole to Bari Chaupar covering a distance of 2.349 km.

There will be three underground and eight elevated stations in the first phase. The total expenditure on this phase of the project would be about Rs 3,149 crore.

Likewise, in the second phase, the Metro train would run from Sitapura to Ambabari covering a distance of 23.099 km on which Rs 6,581 crore would be spent.

There would be five underground and 15 elevated stations in the second phase.

The state government had given the work of the first phase of Jaipur Metro to Delhi Metro Rail Corporation (DMRC) on Aug 5, 2010.

The operation and maintenance of first phase would be carried by the newly-formed Jaipur Metro Rail Corporation.

DMRC has already given the order for the supply of rolling stock (rail wagons) to BEML and has also given the work order to a company for signalling and telecom supply.

According to official information, the state government has to acquire 50 hectare land for the project. Of this, the state government has already transferred 23.69 hectare land and the remaining 26.31 hectare land is soon to be identified and transferred.

The work on the second phase of the project is proposed to be done on public-private partnership (PPP) model. For this, requests for quotation (RFQs) have already been issued and after the technical evaluation of the RFQs, four national and multi-national companies, including Reliance Infrastructure Limited, Gammon Infrastructure-Iridium Concession, Soma-ICF and Essar projects-Samsung C-NT, have been selected for requests for proposal (RFPs).
.