This Article is From Oct 16, 2013

Kudankulam nuclear plant power generation again delayed

Kudankulam nuclear plant power generation again delayed

The Kudankulam Nuclear Power Plant

Chennai: India's atomic power plants operator Nuclear Power Corporation of India (NPCIL) now hopes the first 1,000 MW unit at Kudankulam Nuclear Power Project (KNPP) will start commercial operations next month.

The People's Movement Against Nuclear Energy (PMANE) protesting the KNPP location has demanded closure of the non-functional units at the plant.

The PMANE has also called for an agitation on October 20 when Prime Minister Manmohan Singh leaves for Russia to sign an agreement for two more reactors.

According to NPCIL, the expected date of commercial operation of the first unit is November 2013 and the unit has achieved 99.76 per cent physical progress as of September 2013.

The NPCIL is setting up two 1,000 MW Russian reactors at Kudankulam in Tirunelveli district, around 650 km from here. The total outlay for the project is over Rs.17,000 crore.

KNPP is India's first pressurised water reactor belonging to the light water reactor category.

The first unit attained criticality, which is the beginning of the fission process, for the first time in July 2013.

In August, the Atomic Energy Regulatory Board (AERB) gave its nod to KNPP to raise the reactor power levels to 50 percent and synchronisation of the unit with the power grid.

The NPCIL earlier said it would connect the first unit to the grid end-August, generating 400 MW power.

But that did not happen due to two condenser valve problems which seemed to have got stuck.

Sources said the problem of a school of jelly fish choking the sea water intake had been sorted out long back and the current problem is not related to that.

According to sources, sufficient pressure is not being built to run the turbine to generate power.

"The nuclear authorities have been announcing the start date of KNPP-1 from the year 2005 onwards. The prime minister himself announced the start of the project a few times in December 2011 and March 2013. None of these dates were honoured and the project is unable to breathe even today," PMANE charged in a statement Wednesday.

"Instead of telling the nation the complete truth about the project, the prime minister, his ministerial colleagues and the nuclear authorities are competing with each other to announce fresh dates of electricity generation," the statement added.

Interestingly the AERB's clearance to increase the reactor power levels and synchronisation is valid only till Jan 31, 2014.

Officials of NPCIL were not available for clarifications on the continued delay in generating power from the first unit.

With the power from KNPP getting delayed, a senior official of Tamil Nadu Generation and Distribution Corporation told IANS that the state power utility does not take into account the atomic power unit in its power plans.

The second unit at KNPP is expected to start commercial operations in June next year. The unit has achieved progress of 96 per cent as of September.

According to sources the activities at the second unit are inching ahead at snail's pace as the focus is on the first unit starting commercial operations.

.