Chennai: Problems with valves in the first unit at the Kudankulam Nuclear Power Project (KNPP) have delayed the synchronisation of the unit with the grid, officials said.
The Nuclear Power Corporation of India Ltd (NPCIL), India's atomic power plant operator, is setting up two 1,000 MW Russian reactors at Kudankulam in Tirunelveli district, around 650 km from Chennai.
After several years of delay, the first 1,000 MW Russian-made reactor at KNPP and India's 21st reactor began its nuclear fission process on July 13.
The 1,000 MW first unit is expected to be synchronised with the grid in 15-days time, they said.
A senior official of the Atomic Energy Regulatory Board (AERB) told IANS: "The performance of some parts can be checked only when the power generation is increased to certain levels."
"While we have issued clearance for the first unit to generate 50 percent power tests have to be done simultaneously and corrective action are taken."
He said the systems will be checked while increasing the power levels.
"Till the unit gets stabilised at a certain level, power generation will be increased and decreased," he said.
"Two valves inside the condenser in the first unit seems to have got stuck and they were later set right.
"NPCIL officials had to go to the root cause of the problem so that it does not occur again which in turn has taken time," a source told IANS.
The NPCIL started its work at the KNPP's first unit, soon after receiving AERB's clearance, so as to connect the unit to the grid when it generates 400 MW power.
KNPP site director R.S. Sundar earlier said the first unit would be connected to the grid by the end of August, generating 500 MW. But that did not happen perhaps due to the condenser valve problem.
After necessary regulatory clearances, power generation will be increased gradually to 50 percent, 75 percent, 90 percent and finally 100 percent.
The Nuclear Power Corporation of India Ltd (NPCIL), India's atomic power plant operator, is setting up two 1,000 MW Russian reactors at Kudankulam in Tirunelveli district, around 650 km from Chennai.
After several years of delay, the first 1,000 MW Russian-made reactor at KNPP and India's 21st reactor began its nuclear fission process on July 13.
A senior official of the Atomic Energy Regulatory Board (AERB) told IANS: "The performance of some parts can be checked only when the power generation is increased to certain levels."
Advertisement
He said the systems will be checked while increasing the power levels.
Advertisement
"Two valves inside the condenser in the first unit seems to have got stuck and they were later set right.
Advertisement
The NPCIL started its work at the KNPP's first unit, soon after receiving AERB's clearance, so as to connect the unit to the grid when it generates 400 MW power.
Advertisement
After necessary regulatory clearances, power generation will be increased gradually to 50 percent, 75 percent, 90 percent and finally 100 percent.
Advertisement
COMMENTS
Advertisement
Shivam Dube Hails Rohit Sharma, Rahul Dravid For 'Unwavering Support' Madras High Court's Big Rebuke To Probe Agency In Illegal Sand Mining Row Chennai Schools Receive Bomb Threat E-Mail, Cops Launch Probe World's Largest Isolated Tribe Makes Rare Appearance In New Footage 4 Passengers Die As 12 Coaches Of Chandigarh-Dibrugarh Express Derail In UP Why BJP Lost Lok Sabha Polls In Uttar Pradesh - 6 Reasons In Party Report Sensex Breaches 81,000 Mark, Nifty Scales 24,800 Peak On IT, FMCG Gains 'Yodha' Is A Mammoth Documentation Of India's Wars And Battles Woman Dies After Jumping Off Elevated Platform At Delhi Metro Station: Cops Track Latest News Live on NDTV.com and get news updates from India and around the world.